Ehlert Expansion and Renovation of Warehouse in Verl
Object location
Verl
Service scope
Turnkey
Building type
Logistics Building
Floor space
4.018 m²
Measurements
92 / 48 / 14,05 m
Construction period
Jan. 2017 to Jun. 2017
Object description
The first construction phase, completed by BREMER in 2013, is being expanded with a second phase. The second phase includes an additional logistics area with two mobile racking systems for 6,572 pallet spaces, a goods receiving area with five delivery gates, a covered waste container station, and an additional forklift charging station. On the upper floor, an existing mezzanine area will be expanded to accommodate additional office workspaces.