Skip to main content Skip to page footer

SEBRO Production Facility Kirchardt

Object location

Kirchardt

Service scope

Turnkey

Building type

Production Facility

Floor space

5.527 m²

Measurements

81 / 102 / 10,50 m

Construction period

Mar. 2017 to Dec. 2017

Object description

The new building consists of two adjoining production halls and a two-storey office building as the head building to Hall 1. The office and the production hall are separated by a firewall. The foundation is a deep foundation to a depth of approx. 10 m. The production halls will have a total of 3 spiral high-speed doors. A handicapped-accessible elevator will be installed in the office building. The façade of the production halls will be designed as a vertical insulated façade, the office façade with a thermal insulation composite system. The halls will be heated by gas-fired radiant heaters, while the office building will be heated by a heat pump and a gas condensing boiler system.

Special features

New building consisting of two adjoining production halls and a two-storey office building as the head building to Hall 1. The office and production hall are separated by a firewall. The foundation is a deep foundation to a depth of approx. 10 m. The production halls will have a total of 3 spiral high-speed doors. A handicapped-accessible elevator will be installed in the office building. The façade of the production halls will be designed as a vertical insulated façade, the office façade with a thermal insulation composite system. The halls will be heated by gas-fired radiant heaters, while the office building will be heated by a heat pump and a gas condensing boiler system.

SEBRO Maschinenteile GmbH

»Für die tolle Planung sowie die recht sportliche Baugeschwindigkeit in sehr guter Ausführungsqualität möchten wir uns bei Ihnen und allen beteiligten Mitarbeiten von BREMER Bau sowie Ihren Unterauftragnehmern recht herzlich bedanken. Im Falle von zukünftig geplanten Bauvorhaben würden wir sicherlich sehr gerne wieder auf Sie und Ihr Team zukommen.«

Location

Stuttgart

You are impressed by our reference and would like to know which BREMER office managed this project?

Learn more

Similar projects

Chefs Culinar Logistikzentrum Bueren
  • Head office Paderborn
  • Cold Storage Facilities
  • Ongoing
FOUR PARX Gewerbecampus Muenchen-Kirchheim
  • Head office Paderborn
  • Logistics Buildings
  • Ongoing
R+M Suttner Produktions- und Entwicklungsstandort Lemgo
  • Head office Paderborn
  • Office Buildings
  • Completed