Lorenz Bahlsen Production Hall Hankensbüttel

Object location

Hankensbüttel

Service scope

Turnkey and Revitalisation

Building type

Production hall with office building

Floor space

3.879 m²

Measurements

63 / 32 / 15 m

Construction period

June 2025 - June 2026

Object description

The team at BREMER Nord GmbH is constructing a new production hall with office space for the food manufacturer Lorenz Bahlsen.

Project Features & Challenges:

Demolition of the existing halls, followed by reassembly on the company premises – whilst operations continue.

Due to the nature of the food industry, very high hygiene standards apply. Small building site: the new hall must be cleverly integrated into existing structures.

Flooring solution: a fully coated floor with high slip resistance that is also very easy to clean – a key requirement in food production.

Integration of logistics areas with offices – functional, efficient and future-oriented.

The new hall is optimally designed for logistics processes, improving material flow and working conditions – without interrupting ongoing operations.

The construction period is 12 months.

Construction webcam

The image shows the current construction progress and is updated every 15 minutes.
The image shows the current construction progress and is updated every 15 minutes.

Location

Hamburg

You are impressed by our reference and would like to know which BREMER office managed this project?

Learn more

Similar projects

Stadt Büren Feuerwehrhaus Steinhausen
  • Head office Paderborn
  • Building in existing struktures
  • Ongoing
Stadt Büren Feuerwehrhaus Hegensdorf
  • Head office Paderborn
  • Building in existing struktures
  • Ongoing
R+M Suttner Produktions- und Entwicklungsstandort Lemgo
  • Head office Paderborn
  • Office Buildings
  • Completed