Amazon Logistics Centre Horn-Bad Meinberg
Object location
Horn-Bad Meinberg
Service scope
Turnkey
Building type
Office + Logistics Buildings
Floor space
189.995 m²/ 43.603 m²
Measurements
303 / 186 / 27,27 m
Construction period
Sept. 2022 to July 2024
Object description
BREMER AG is building a new logistics center for the developer Amazon at the Horn-Bad Meinberg location.
The building will cover an area of approximately 51,280m2, on which a state-of-the-art logistics center with 4 levels will be created. Products will be stored there and office and social areas will be available for employees. The latest technology is used in the logistics center. Very specifically: transport robots that drive mobile shelves to employees in the storage and retrieval of goods. This reduces walking distances. The site will have 791 parking spaces for employees, 74 of which will be equipped with electric charging stations. Furthermore, 80 bicycle parking spaces and around 220 truck parking spaces will be created, including 20 buffer parking spaces for trucks that arrive too early. To enable employees to connect to local public transport, two bus stops are planned for the building.
During construction, the latest environmental standards in terms of energy efficiency and the responsible use of resources are used. For example, a photovoltaic system will be installed on the roof of the site. Amazon has also applied for gold certification from the German Sustainable Building Council (DGNB).
You can find more information about Amazon logistics on the company blog: aboutamazon.de/logistikzentren
Special features
News from construction and current activities
- Setting up the construction site and initial earthworks (by spring 2023): Construction started in March 2022 with preparatory measures and initial earthworks that are expected to be completed in spring 2023. This includes cut & fill work and the creation of gravel surfaces, construction roads and construction site access roads. Special foundation work
- (Nov 2022 - March 2023): Approximately 2,000 concrete driven piles are driven into the ground from the gravel working level created. Foundation work
- (December 2022 - June 2023 ): Between December 2022 and September 2023, the individual and strip foundations will be manufactured as preliminary work for the assembly of prefabricated parts. Assembly of prefabricated parts
- (December 2022 - end of 2023): The 'framework' of the building is erected with the prefabricated parts. The pre-assembly of in-situ concrete stiffening walls will take place from December 2022 to early spring 2023. The main assembly of the prefabricated parts from late spring 2023 to the end of 2023.